|
Newsletter
October
2001
DEPARTMENT
OF ENVIRONMENTAL PROTECTION
BUREAU OF RESOURCE PROTECTION
WETLANDS AND WATERWAYS PROGRAM
1 WINTER STREET, BOSTON MA 02108
DRAFT SUMMARY MASSACHUSETTS INLAND WETLAND REPLICATION
GUIDELINES: A DRAFT SUMMARY OF KEY POINTS
THE
NEED FOR GUIDANCE
A recent study conducted by the University of Massachusetts
found that the majority of wetland replication projects
undertaken in the Commonwealth do not meet the minimum performance
standards in the Wetlands Protection Regulations.
The
study summarized the reasons for the lack of success of
replication sites as follows:
1) Inadequate wetland hydrology;
2) Poor vegetation replanting plans; or
3) Replication areas built smaller than required in the
plans.
As
a result, the Department of Environmental Protection (DEP)
has developed guidance to aid in improving success rates
of replication areas. Specifically, this replication guidance
was written to help applicants prepare freshwater replication
plans to comply with the Wetlands Protection Act (WPA) Regulations
for bordering vegetated wetlands (310 CMR 10.55 (4)) and
Section 401 of the Clean Water Act pertaining to Water Quality
Certification (314 CMR 9.06(2)). An outline of the draft
document is provided below.
If
you would like a full copy of the draft document for review
and comment please contact:
Lisa
Rhodes
DEP Wetlands Program,
1 Winter Street, Boston MA 02108
(617) 292-5512; FAX (617) 292 – 5696;
Email: Lisa.Rhodes@state.ma.us
Final copies will be distributed to all Conservation Commissions.
DISCRETIONARY
AUTHORITY
WPA regulations allow Conservation Commissions to approve
up to 5000 square feet of bordering vegetated wetland (BVW)
loss at their discretion (310 CMR 10.55(4)(b)). Replication
should be required for all projects with unavoidable wetland
loss including limited projects where possible. Decision-making
under this discretionary authority should involve replication
design considerations prior to approval of the replication
plan.
It
is often more cost effective to design a project to avoid
wetland impacts than to propose replication, since the requirements
to ensure a successful replication area can often take many
years and dollars to complete.
SEQUENCING
Replication is the final step in the process of
wetland mitigation. Wetland mitigation involves reducing
the impacts to wetland resources through a three-step process
often referred to as “sequencing” as follows:
1) Avoidance of wetland impacts;
2) Minimizing necessary impacts as much as possible; and
3) Replicating losses that cannot be avoided.
Conservation
Commissions should follow these steps when evaluating a
project involving wetland replication.
PUBLIC
INTERESTS
For unavoidable impacts, the replication area
should be designed to provide compensation for the public
interests served by the existing wetland (public and private
water supply, groundwater supply, flood control, storm damage
prevention, prevention of pollution, fisheries, and wildlife
habitat). The replication area design should also incorporate
the opportunities and limitations of the mitigation site.
IMPORTANT
COMPONENTS: HYDROLOGY, SOILS AND VEGETATION
Hydrology
Proper
hydrology of the replication site is critical to a successful
replication project. The final replication surface and ground
water elevations are predicated on establishing site hydrology.
High and low ground and surface water elevations must be
established from data gathered in the local area. Applicants
should begin data collection activities as far in advance
of the project as possible.
-
Understanding hydrology requires knowledge of the anticipated
seasonal groundwater depth, and the duration and frequency
of both inundation and saturation (hydroperiod). This
information should be described and compared to water
regime characteristics for the proposed plantings.
Ideally,
replication areas should not depend only on precipitation
and sheet runoff. Successful replication areas require a
seasonal source of groundwater as well as contributions
from a surface water source.
-
Only the flood storage that the existing BVW provides
should be designed in the replication areas. Additional,
compensatory flood storage from upland floodplain should
not be allowed in replication areas, unless it can be
demonstrated that spring floods will not impact the replication
area. Impacts from flooding can include inundation for
extended periods, scour and deposition. Compensatory flood
storage for all floodplain impacts, however, is required
to be provided at the site of the impact.
-
In the event that a “constructed wetland”
is used for stormwater purposes, the area shall not be
included as replication credit for an impacted wetland
resource area. If any stormwater is to be directed to
a bona-fide replicated wetland, the stormwater is required
to be treated prior to discharge in accordance with the
Massachusetts Stormwater Management Policy.
Soils
-
The reuse of hydric soils from the impacted wetland to
the replication area is preferred. Plans should include
descriptive soil profile information from test pits (e.g.
horizons, texture, organic matter, Munsell hue, value,
chroma, and evidence of hydrologic influence).
-
Soil taken from areas where invasive species such as Phragmites
and Purple Loosestrife are present should be avoided,
especially if the invasive species represent a dominant
monoculture. If soils are used where any invasive species
are present, then the applicant does so at their own risk
and may be responsible for remediation.
-
Surveying of sub grades and finished elevations should
be conducted frequently during construction to inspect
for soil settling and compaction.
- Mitigation
sites that are constructed on dense compacted C-horizons
with a thin layer of A or O placed on top are at risk
of failing. The goal for soils at the mitigation site
should be to create soil profiles that approximate as
closely as possible the soil profiles at the impact site
(or nearest adjacent wetland).
-
Although not required, use of redox and pH meters in the
replication area and adjacent wetlands will aid in replication
success by allowing the applicant to make assumptions
as to the likely success of long term hydric soil development
and function.
-
Excavated hydric soils to be used at the mitigation site
should be placed in the mitigation area as soon as possible
to avoid dehydration. (if storage is required, soils should
be stockpiled for as little time as possible and kept
wet).
Vegetation
-
Plantings can be taken from the impacted wetland or brought
from off-site. In either case, plans should provide detailed
descriptions of the techniques proposed to establish vegetation,
including methods for maintaining seed viability, rootstocks
and plants during transplantation.
-
Plants should be kept moist and planted within one day
of removal from existing wetland or as soon as possible.
Consideration should be given to leaving existing mature
upland trees on humocks within the replication site. Vegetated
hummocks provide shade to the surrounding replication
area and provide varied topography for wildlife habitat.
-
All planting should occur at the beginning or end of the
growing season. Fall plantings should be done before the
first frost. Shrubs and trees, however, may be planted
up to November 15, weather permitting.
The
regulations require that at least 75% of the surface of
the replacement area shall be reestablished with indigenous
wetland plant species within two growing seasons. In order
to accomplish this, the hydrology and soil conditions must
be appropriate for the types of vegetation proposed.
PERMIT
APPLICATIONS
Applicants should provide the following information as part
of their permit application:
-
Narrative descriptions of the wetland to be altered and
the proposed wetland replication site;
-
Plan at scale of 1”=10’ to 1” = 40’
with contour lines at 1-foot intervals, including surveyed
flag locations, benchmarks, or structures;
-
Surface area calculation;
-
Elevation and vegetation planting cross-sections.
CONSTRUCTION
AND MONITORING
-
When possible, the replication area should be excavated
and graded to the specifications in the plan before work
in the existing wetland begins.
-
As part of the wetland construction process, site visits
should occur at the following stages:
1. Before excavation work begins in order to inspect
site flagging;
2. Before placement of hydric soils in replication area
in order to inspect excavated elevations and likely
post-construction ground water elevations for the replication
area;
3. After each stage of grading work is completed to
inspect for soil settling, compaction, and finished
elevations;
4. During planting and seeding and after the first month
of the growing season to inspect propagation techniques;
5. After one growing season to observe vegetation development
and regulatory compliance;
6. After two growing seasons to determine vegetation
development and regulatory compliance;
7. After subsequent growing seasons, if a greater than
2-year monitoring program is required.
The
Certificate of Compliance should not be issued until regulatory
compliance is achieved.
APPENDICES
-
Sources of Planning Information
-
Replication Checklist
-
Example Monitoring Data Sheet
-
Common Mistakes and Problems
-
USDA Growing Seasons
CONTACT
FOR FURTHER INFORMATION
If you would like a full copy of the draft document for
review and comment please contact:
Lisa Rhodes
DEP Wetlands Program,
1 Winter Street, Boston MA 02108
(617) 292-5512; FAX (617) 292 – 5696;
Email: Lisa.Rhodes@state.ma.us
Final copies will be distributed to all Conservation Commissions.
Comment
on this Article
>>
Go to Top
<< Back to Newsletter
|